Full Bathroom Remodeling in Burlingame, CA: Scope, Timeline, and Cost
A full bathroom remodeling in Burlingame typically runs $9,000 – $28,000 and takes three to five weeks once demolition starts. That covers gutting the room to studs, rebuilding the wet zone, new tile, a new vanity, fixtures, ventilation, and finish electrical. Homes in Burlingame’s older core often stretch toward the top of that range because opening walls exposes wiring and framing that nobody priced until it’s visible. Call (833) 997-7759 for a free on-site estimate with a written, line-item scope before any demo begins.
How a Full Bathroom Remodel Actually Runs, Day by Day
Every full bath follows the same order. Skipping or compressing a stage is where remodels go sideways, so this is the sequence we hold to:
- Days 1 – 2: Demolition and discovery. We pull the fixtures, tile, and drywall down to framing and subfloor. The moment the wall is open, we photograph everything and show you what we found: old wiring, a rotted subfloor, a vent that runs nowhere. Any change gets a written change order before work continues, so the number you see stays the number you pay.
- Days 3 – 6: Rough-in. Plumbing lines are relocated or replaced, electrical is run for outlets, lighting, and a GFCI circuit, and the exhaust fan ducted to the exterior wall rather than into the attic. We schedule the rough inspection, since a fully reconfigured bathroom requires permits pulled and inspections passed.
- Days 7 – 12: Waterproofing and tile. Cement backer board or a bonded waterproof membrane goes up, seams and corners taped and sealed, then tile. This is the stage where amateur work shows up two years later as a leak in the ceiling below, so we don’t rush it.
- Days 13 – 18: Setting and finish. Vanity set and leveled, toilet and shower trim installed, mirrors and hardware hung, paint finished. This is where you make the calls you deferred – tile pattern, fixture finish, paint color – so have them locked two weeks before this stage.
- Final walkthrough. We test every supply and drain, run the fan, check the tile layout against the plan, and hand over the written warranty. If it’s not done right, we make it right, and that’s covered under our 730-Day Done Right Promise.
Want to see how the bathroom fits a larger plan, like a primary suite or an ADU conversion? Our Bathroom Remodeling service hub lays out the broader scope.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices That Actually Drive Your Remodel
Full bath decisions come down to a handful of forks. Each one changes both price and how the room holds up:
- Tile material: Porcelain is the workhorse – dense, water-resistant, and priced reasonably. Natural stone like marble or travertine looks richer but needs sealing and is more prone to etching. For a Burlingame bath used daily, porcelain with a stone-look finish often reads high-end without the maintenance.
- Shower system: A tiled shower with a linear drain and a frameless glass panel is the current standard. A curbless design costs more in floor and waterproofing work but opens the room up. Both outperform a fiberglass insert on resale value.
- Vanity: Stock cabinets keep costs down; semi-custom built-ins let you fit an odd wall in an old house. We work with KraftMaid and Kohler cabinetry and fixtures where spec matters.
- Ventilation: A properly ducted, sized exhaust fan is not optional in Burlingame’s damp winters. Undersized fans leave moisture in the walls.
- Layout: Keeping the toilet and tub in the same footprint saves plumbing labor. Moving them opens possibilities but adds cost and inspection complexity.
What Full Bathroom Remodeling Costs in Burlingame, CA
Expect $9,000 – $28,000 for a full bathroom remodel here. The spread is wide because the variables are real:
| Line item | Typical range |
|---|---|
| Full bathroom remodel (gut to finish) | $9,000 – $28,000 |
| Walk-in shower installation | $4,500 – $12,000 |
| Tub-to-shower conversion | $3,500 – $10,000 |
| Bathroom vanity installation | $800 – $3,000 |
What pushes a job toward the high end: relocating plumbing or electrical, structural changes like moving a wall, stone tile with detailed patterns, a larger footprint, and any hidden condition found once walls open. The low end suits a compact hall bath with the original layout kept, porcelain tile, and a semi-custom vanity. Your written estimate covers permits, materials, labor, and cleanup; what it can’t include is a condition nobody can see until demo. We flag that boundary in writing before we start, then price any discovery with a change order you approve first. Our Bathroom Remodeling in Burlingame page explains how this fits into a whole-home plan.
See the difference
Before
After
Before
After
Before
AfterWhat Burlingame’s Older Housing Stock Does to This Job
Burlingame is one of the Peninsula’s most architecturally protected suburbs, and its core is dominated by early-1900s through 1940s single-family homes – Craftsman bungalows, Spanish Colonial Revival, and Tudor cottages in Easton Addition and Burlingame Park. In these houses, opening a bathroom wall regularly reveals stacked remodel layers on top of original framing: old wiring, pier-and-beam subfloor irregularities, and venting that was never run correctly. That discovery is why contractors in this city need to plan for code upgrades the drawings never showed. Burlingame’s cool, fog-influenced climate and damp winters also make interior moisture control serious business, so ventilation and waterproofing are non-negotiable. We cover the whole city here and in the Burlingame service-area pages, ZIPs 94010 and 94011 included.
Serving Burlingame, CA – Our Local Coverage Area
We serve Burlingame and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – Full Bathroom Remodeling in Burlingame
Most run three to five weeks from demo to walkthrough. Historic homes and any layout change push toward the longer end because of inspection scheduling and discovery work.
Yes, any remodel that moves plumbing, electrical, or structural elements requires a permit and inspections. Cosmetic-only tile swaps may not. We pull the permits and manage the inspections for you.
Yes. Keeping the toilet, tub, and vanity in the existing footprint is the most cost-effective path and still delivers a fully updated bathroom. Moving plumbing is optional and adds to both budget and timeline.
Typically $9,000 – $28,000, with the final number driven by size, layout changes, material grade, and what’s behind the walls. Call (833) 997-7759 for an exact quote – estimates are free.
Our 730-Day Done Right Promise covers the workmanship on your Burlingame bathroom remodel. If something fails due to our installation, we come back and fix it.
Get a Free Estimate for Your Burlingame Bathroom
We’ll walk the room, check the plumbing and electrical, and hand you a written line-item estimate with a fixed price – no change orders after you approve it. Call (833) 997-7759 to schedule your free on-site estimate for full bathroom remodeling in Burlingame. A live person answers, every day of the week, and we’ll answer every question before you commit to anything.