Junior ADU & Interior Conversion in Burlingame: What It Costs and How Long It Takes
A junior ADU and interior conversion in Burlingame typically runs $45,000 – $130,000 and takes 10 – 16 weeks from permit to final inspection, depending on how much of the existing interior you reconfigure. A JADU is the smaller, simpler cousin of a full ADU: up to 500 square feet, carved out of existing space rather than built new, usually with a kitchenette and its own bathroom entrance. Call (833) 997-7759 to schedule a free on-site estimate and get a written, line-item scope for your Burlingame home.
How the Job Actually Runs, Stage by Stage
Most contractors wave at a JADU like it’s a weekend project. It isn’t. Here’s the real sequence we follow on a Burlingame conversion, with the durations and decision points homeowners care about.
Stage 1: Feasibility and design, weeks 1 – 3
We start by walking the space you want to convert and checking what’s behind the walls: foundation type, wiring era, plumbing runs, and ceiling height. On Burlingame’s older stock that survey often turns up surprises, and we price the likely upgrades before drawings are done. You decide the layout at this stage (bedroom-and-bath suite versus studio with kitchenette), and that decision drives everything downstream.
Stage 2: Permits and drawings, weeks 3 – 7
Burlingame reviews JADU plans against state ADU rules plus local design review, so this is the slowest phase and the one most likely to stall a less-prepared applicant. You sign off on the final plan set and we submit. Realistic turnaround here is four to six weeks; if the home is in a historic-district context, add time. You decide the finish schedule while we wait, not after.
Stage 3: Demolition and rough-in, weeks 7 – 10
Demo comes first, then framing adjustments, then the trades: electrical, plumbing, HVAC, and any foundation bolting or shear work the plan calls for. This is the stage where opening a wall reveals stacked remodel layers from prior decades. You approve any change order in writing before we proceed, at a fixed price, not a verbal “we’ll see.”
Stage 4: Insulation, drywall, and finishes, weeks 10 – 14
Insulation and drywall close the walls, then flooring, tile, cabinetry, and fixtures go in. You confirm paint colors, tile, and hardware here. Most owners find the finish schedule the most decision-heavy stretch, so we hand it over early and keep it moving.
Stage 5: Final inspection and walkthrough, weeks 14 – 16
We schedule the final inspection, correct any punch-list items, and walk the space with you. Every JADU we build is covered by our 730-Day Done Right Promise, so if something isn’t right after you move in, we come back and make it right.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Weigh Before We Start
A JADU lives or dies on the choices you make up front. Here’s what actually matters on a Burlingame conversion:
- Kitchenette versus full kitchen: A JADU only needs a sink, a small fridge, and a microwave or cooktop. Skip the range and you save on venting and electrical; add it and you gain rental flexibility. We’ll show you both layouts.
- Bathroom configuration: A half-bath keeps costs down but narrows who can live there. A walk-in shower with a curbless pan runs more but works for aging parents and long-term tenants. This is often the single biggest line item.
- Wet-wall placement: Keeping the new bathroom against an existing plumbing wall saves thousands. Moving the drain across the room means cutting and re-pouring, which you’ll feel in the budget.
- Windows and doors: On Burlingame’s damp, foggy mornings, a well-sealed exterior door matters. We often spec Therma-Tru or ECO Window Systems for conversions where drafts and moisture are a concern.
- Flooring: Luxury vinyl plank handles a wet bath entrance best; hardwood looks warmer but needs care near water. We’ll talk through what suits your use.
What Junior ADU & Interior Conversion Costs in Burlingame, CA
The range for this job here is $45,000 – $130,000. That spread is wide because a JADU is really a small remodel wearing a different hat, and the variables below swing it hard.
- Size and scope: A tight studio conversion sits near the bottom; a full bedroom-plus-bath-plus-kitchenette suite with a separate entrance climbs toward the top.
- Existing condition: Burlingame’s early-1900s to 1940s homes often carry original wiring and pier-and-beam foundations, so opening a wall triggers code upgrades the drawings didn’t anticipate.
- Moving plumbing or structure: Relocating a drain or cutting a new opening in a load-bearing wall adds real cost. Keeping the wet wall in place is the cheapest path to a solid JADU.
- Material grade: Builder-grade cabinetry and stock tile versus semi-custom options can move the number by $10,000 – $20,000 on its own.
- Permit and inspection scope: Design review, historic scrutiny, and required upgrades all carry fees and time.
A written estimate from us lists every line and holds to it, with 0% financing for 18 months and $1,000 off projects over $10,000 to ease the upfront. What we don’t include is furniture or appliances you source yourself, or landscaping outside the conversion footprint.
See the difference
Before
After
Before
After
Before
AfterWhat Burlingame Homes Specifically Do to This Job
Burlingame is one of the oldest and most architecturally protected suburbs on the Peninsula, and that changes a JADU job. In Burlingame Park, Downtown, and Easton Addition, you’re working inside Craftsman bungalows, Spanish Colonial Revival homes, and Tudor cottages from the early 1900s through the 1940s, and a conversion has to respect detailing that a modern build never confronts. Because the city reviews additions and conversions against historic-preservation standards, we plan the design review from day one, not after a rejection. The fog-influenced summers and damp winters here mean exterior doors and flashing on the conversion entrance carry more weight than they would inland. And on the older homes, prior remodel layers stacked on original framing mean opening a wall for the JADU reveals foundation bolting, shear, and electrical upgrades the drawings didn’t foresee. We cover all of Burlingame, including ZIP codes 94011 and 94010.
Serving Burlingame, CA – Our Local Coverage Area
We serve Burlingame and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked, Junior ADU & Interior Conversion in Burlingame
Plan on 10 – 16 weeks from permit to final inspection, with permitting itself taking four to six weeks and historic review adding time. Call (833) 997-7759 and we’ll give you a realistic schedule for your specific home.
Yes. A JADU requires permits for the conversion, the bathroom, the kitchenette, and any electrical or plumbing changes, and the city reviews the plan against state ADU rules and local design standards. We pull the permits and manage inspections so you aren’t chasing the city alone.
Often yes, and that’s the smartest way to keep the budget down. If an existing bathroom wall or drain line can serve the new JADU, we build around it and save you thousands. When a move is unavoidable, we’ll tell you what it adds before work starts.
Expect $45,000 – $130,000, with the low end being a studio conversion reusing existing plumbing and the high end a full suite with a separate entrance and upgraded finishes. Call (833) 997-7759 for an exact quote; estimates are free.
Every conversion we complete is backed by our 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something isn’t right within that window, we return and make it right.
Schedule Your Free Junior ADU Estimate
If you’re planning a Junior ADU & Interior Conversion in Burlingame, the first step is a free on-site estimate. Call (833) 997-7759 and a live person answers, day or night. We’ll walk the space, talk through layout options, flag what the home’s age might reveal, and hand you a written, line-item price with no surprises. Some owners pair the JADU with Kitchen Design & Layout in Burlingame or a wider scope under Home Additions & ADU in Burlingame; others fold it into Home Additions & ADU planning or pair it with Small & Partial Kitchen Remodels in Burlingame.